Check out our plan to make Siskiyou Street safe, clean and beautiful. What are your ideas to help eliminate street flooding, excessive speeding and to make Siskiyou Street a beautiful and inviting corridor. Join the community effort to improve the intersection at 77th Avenue and Siskiyou Street.

Write your thoughts here, then join us for our weekly gatherings Saturday mornings, 10:00 a.m. at 3105 NE 77th Avenue for coffee, snacks and planning.

Wednesday, March 10, 2010

A sunny day. Short meeting. Great work.

Siskiyou Passage: Working Notes, March 6, 2010 meeting.
“The end is nothing; the road is all.”
–Willa Cather

Held on a beautiful sunny spring morning resulting in light attendance –
And great work in very short order.

Report on Open Community Garden. All are welcome to attend the Open Community Garden event at Madison High School on Friday March 12th beginning at 3:30 PM - the kick-off for a week long event concerning food production. Learn about the National Food Coalition, the Oregon Food Bank and localized food production.

Report on City Repair. Apathy Rehabilitation Place at Sea Change Gallery. Feeling the ‘Siskiyou Passage’ project blahs? Rejuvenate your spirit and ‘wake up refreshed’ (or begin kissing strangers) at the Apathy Rehabilitation Place. Check out www.cityrepair.org “Public Events” for the March calendar of events at Sea Change Gallery, 625 NW Everett Street.

Design Report and Concepts. In honor of the beautiful morning and a primal need to get outside, the stalwarts in attendance moved through business quickly. The group looked over the design concepts prepared by Genevieve, Rosemary & Sally, reviewed the committee’s report and made some critical decisions.
Design Foundation.
1. The basic design elements are:
  • A ‘compass’ street painting in the intersection of Siskiyou and 77th,
  • Rock cairns anyone can create in their own parking strip or front yard, and
  • A community information board on Sally’s parking strip.
  • (The stormwater swale in Sally’s parking strip is on hold while we apply for city Green Streets grant funding.)
2. Less is more – The final design should evoke the various meanings surrounding a passage but the design itself should be simple and easy to install and maintain.
3. The design motifs should be natural elements and should relate to ‘Siskiyou’, the neighborhood and/or a passage. Favored motifs include: leaves, plants, fish, foot prints, and ‘Six Rocks’. One example discussed was: The center of the compass could be a stylized ‘Dream-catcher’ which could be painted to suggest a rose – playing on the Roseway neighborhood connection and Roseway Heights School.
4. Colors should be ‘analogous’.
5. If possible, the painting should have visual depth. (That might slow traffic down!)
Design Timeline.
  • 3/15 - 1st meeting with Portland Bureau of transportation (PBOT) to talk about permits.
  • 3/25 - Meeting at Sea Change Gallery to talk about preliminary design
  • 4/8 - Preliminary design submitted to City Repair
  • 4/15 - 2nd PBOT meeting regarding permits
  • 4/22 - Final design submitted for review and approval by City Repair
  • 5/6 - Final PBOT approval of design and permits
  • 5/8 - 5/9 - First street work days
  • 5/22 - 5/23 - Final street work and party
Technical Issues.
  • Can the street be sealed first?
  • We need to notify all property owners on each of the four blocks leading into the intersection of Siskiyou and 77th 30 days in advance of the project.
  • We need to work with all affected neighbors to resolve any concerns that may arise regarding the project. The inability to resolve such concerns may be grounds for revocation of the permit by the City Traffic Engineer.
  • Someone should take ownership of the community information board design and construction - even if it is only a temporary board for posting project information.
  • The USFS issues plant gathering permits – this may be a cheap source of native plants.
Volunteers!
—Task (Volunteer)—                       
Green Streets grant application for rain swale (Sally, Eric)
Get ‘Guidebook for Street Painting’ (Done)
Refine compass design (Genevieve, Rosemary, Shawn)
Get price for street sealant (Raphael)
Get paint costs (Rosemary)
Community bulletin board design (WHO??)
Temporary project information board (WHO??)
Locate source of free rocks for cairns for whomever wants them (WHO??)
Next round of City Repair meetings (Thursday evenings) (WHO??)
Next Steps.
  • March 11th – City Repair meeting re: design update and progress report – VOLUNTEER NEEDED.
  • March 13th – Short (<1hour) Siskiyou Passage meeting at Sally’s
    re: update on activity.
  • March 18th – City Repair meeting – Shawn & Jeffrey